Build a Supervisor Roll-Up Gantt in Quickbase With a Timeline Report

A master Gantt across many small work orders doesn't need a plugin. Build a Timeline report on an Assignments table with looked-up work order dates, group it by staff member, filter to current work, and put it on a supervisor dashboard.

A timeline with one band per staff member (Sarah Lee, Mike Chen, Priya Patel) and overlapping work orders highlighted

A question in the Quickbase community, Quickbase Gantt plugin template – summary Gantt chart, asks for a master roll-up Gantt: one supervisor view across lots of small Work Orders (each one acts as a project), where staff members are assigned to several work orders at the same time.

For that kind of roll-up you may not need a Gantt plugin at all. A native Timeline report built across all your work orders and grouped by the person assigned gives supervisors exactly that picture: one band per staff member, one bar per job, and overlaps you can spot at a glance.

A Timeline report grouped by staff member. Each person has a band of bars, one per work order, and overlapping work is easy to see.

This guide covers the data you need, the report setup, grouping and subgroups, a filter for current work, and putting it all on a supervisor dashboard.

What a Timeline needs

A Timeline report works on any table whose records have a start date and an end date. Each record becomes one bar. Grouping then stacks those bars into bands, and you can nest groups inside groups.

So the only real question is: which table has one record per bar you want to see? That depends on how people are assigned.

How work is assignedBuild the Timeline onGroup by
One person per work order, dates on the work orderWork OrdersAssigned person
Dates live on tasks under each work orderTasksWork Order, then Resource (or the reverse)
Several people can be on one work orderAssignments (one record per person per work order)Staff name

The third case is the one in the question, and it's the most common in real crews, so most of this guide uses it.

Set up the data: Work Orders, Staff and Assignments

If one work order can have several people and one person can have several work orders, you need a join table between them. Here it's called Assignments.

Work Orders and Staff each connect to an Assignments table. Assignments looks up the work order's start and end dates, which the Timeline uses.

Work Orders keeps what you probably already have: Work Order Name, Start Date, End Date, Status.

Staff holds one record per person: Full Name, Role, Team. (If everyone is a Quickbase user you could use a user field instead, but a Staff table makes it easy to include people who never log in.)

Assignments holds one record per person per work order. To build it:

  1. Create a new table called Assignments.
  2. Create a relationship where one Work Order has many Assignments. Quickbase adds a Related Work Order reference field to Assignments.
  3. Create a second relationship where one Staff member has many Assignments. That adds Related Staff.
  4. On the Work Orders → Assignments relationship, add lookup fields for Work Order Name, Start Date and End Date. Rename them something clear, like WO Start Date and WO End Date.
  5. On the Staff → Assignments relationship, add a lookup for Full Name (call it Staff Name).
  6. On the Work Order form, add an embedded report of Assignments so whoever schedules the job can add people right there, one row each: Sarah Lee and Mike Chen on WO-1042, Priya Patel on WO-1049, and so on.

Because the dates are looked up, nobody types them twice. When a work order moves, every assignment bar for it moves too.

Optional: when people are only on part of a job

Sometimes Mike Chen only works the first two days of a five-day job. Add two optional date fields on Assignments, Assigned Start and Assigned End, and two Formula - Date fields that fall back to the work order's dates when they're blank:

If(IsNull([Assigned Start]), [WO Start Date], [Assigned Start])
If(IsNull([Assigned End]), [WO End Date], [Assigned End])

Call them Bar Start and Bar End and use them in the Timeline instead of the lookups.

Build the Timeline report

  1. Open the Assignments table, select Reports, then + New report.
  2. Choose Timeline and select Create.
  3. In the timeline section, set the Starting Field to WO Start Date and the Ending Field to WO End Date (or Bar Start / Bar End if you added them).
  4. Pick a resolution. For short work orders, week/day or month/week reads best on a supervisor's screen.
  5. Leave the overall Starting Date and Ending Date blank. Quickbase then sizes the timeline from the earliest start to the latest end in the report, which follows your filter automatically.
  6. Under the fields shown in the bars, choose up to three, for example Work Order Name and Status, so each bar says what the job is.

Don't save yet. Grouping is what turns this into a roll-up.

Group by person (and add a subgroup if you want)

  1. In Sorting & Grouping, choose Sort or group on other columns.
  2. Pick a sort and group option, choose Staff Name, and set the grouping to Equal Values. Each person now gets their own band of bars.
  3. Add a second level to sort by WO Start Date (low to high) so each person's jobs run in date order.
  4. If you'd rather see people grouped under a higher level, hover over the first row, select the plus icon and add another group. Common choices:
    • Team, then Staff Name: a supervisor sees their whole team, person by person.
    • Work Order Name, then Staff Name: the project view, showing who is on each job.
  5. If you group by work order, turn on Sort groups by starting field so the work orders cascade in date order instead of alphabetical order.

You don't need to add the grouping field to the report columns; the group name already appears in the band heading.

If your dates live on tasks instead of work orders, build the same report on the Tasks table: group by Work Order with a subgroup by Resource for a project view, or Resource first and Work Order second for a workload view. Many supervisors find it handy to save both.

Show only current and upcoming work

A roll-up that shows last year's jobs gets long fast. In the report's Filters section:

  1. Choose Show only some of the records.
  2. Add WO End Date is on or after today.
  3. Optionally add Status is not equal to Cancelled (or whatever closed-out statuses you use).

Now each time the report runs it shows only work that's still in progress or still ahead.

Save the report as Shared, give it a clear name like Staff Schedule – Current Work, and choose which roles can see it (your supervisor role at minimum). Add a short description so people know what they're looking at.

Put it on a supervisor dashboard

  1. Open (or create) a dashboard for supervisors and choose to edit it.
  2. Add a Report widget and select Staff Schedule – Current Work.
  3. Give the widget plenty of width; timelines need horizontal space.
  4. Next to it, consider adding the project version (grouped by Work Order) or a small summary report on Assignments that counts assignments per Staff Name with the same filter. That gives a quick "who's carrying the most" number beside the visual.

Reading the view

  • Overlapping bars in one person's band mean that person is booked on more than one job on those days. Sometimes that's fine (a short inspection during a longer job); sometimes it's the thing a supervisor needs to fix.
  • A long, empty stretch in a band means that person has open capacity.
  • A work order that appears under nobody has no Assignment records yet. A quick table report of Work Orders with zero Assignments (add a summary field on Work Orders that counts its Assignments, then filter for 0) catches those.

Quick checklist

  • One record per bar: build on Assignments when several people share a work order
  • Look up WO Start Date and WO End Date onto Assignments (or use formula fallbacks for partial assignments)
  • Timeline with those fields as Starting Field and Ending Field
  • Group by Staff Name with Equal Values; add a subgroup with the plus icon if needed
  • Filter on WO End Date is on or after today
  • Save as Shared and add it to a supervisor dashboard

The original question is in the Quickbase community: Quickbase Gantt plugin template – summary Gantt chart. Quickbase's own help pages on creating a timeline and sorting and grouping reports cover each setting in more detail.